2019 Street Maintenance Program

  July 10, 2019

As part of the City of Alamo Heights Street Improvement Plan, the City has contracted Texas Materials Inc. to perform street work on this year’s Street Maintenance Program. The work will begin on Monday, July 22 through August 16.

 Work will be done as follows – three streets at a time:

  • Oakview, Broadway to N. New Braunfels
  • Tuxedo, Nacogdoches to dead end
  • Lamont, Broadway to Alamo Heights Blvd
  • Columbine, Argo to Lamont
  • Evans, Broadway to Alamo Heights Blvd
  • College, Broadway to Alamo Heights Blvd
  • Alta, Broadway to Alamo Heights Blvd
  • Corona, Broadway to Alamo Heights Blvd
  • Arbutus, Argo to Corona
  • Imlay, Argo to Alta
  • Greely, Argo to Alta
  • Normandy, Broadway to Alamo Heights Blvd
  • Morse, Ogden to Cambridge
  • Broadway and Bike Shop (spot repair)
  • NB Broadway at Ellwood (spot repair)
  • Broadway, Katherine to Harrigan Court (spot repair)

Streets will be closed to thru traffic, but open to residents. As work is being completed, do not park in the street. It is important to keep roadway dry during this process so please be mindful of sprinkler overspray into the roadway.

Please contact the Public Works Department at 210-882-1518 if you have any questions or concerns about this project.