Updated – SAWS – Sewer Rehabilitation at the University of the Incarnate Word

San Antonio Water System – Olmos Basin Central Watershed Sewer Relief Line and Sewer Rehabilitation at the University of the Incarnate Word

Traffic Impacts

  • Work scheduled for June 26th to August 4th – work to be completed between 8:00 AM and 4:00 PM.
  • Patterson will have lane reductions on the following days – June 28th – 29th  July 12th – 13th, July 17th – 18th , July 20th – 22nd, July 31st – August 1st
  • Residents will have access to their homes

Construction Schedule

Posted Plans

patterson

*Dates that are bolded have been added to the lane closure schedule.