Broadway TXDot Improvements – Update

Update – Friday, October 6, 2017

Second Phase of the project will begin on Monday, October 9th.

  • Forming and pouring of driveways and sidewalks
    • Along Broadway from Grove Place to Arcadia
    • At Patterson and Broadway

Work will be completed by Friday, October 13th and will be done from 9 a.m. to 4 p.m.

Alternate lanes of Broadway will be closed during construction/installation.

Monday – September 25, 2017

TXDot will began major street and sidewalk improvement projects at Patterson and Broadway towards Austin Hwy and N. New Braunfels.

The scope of work includes, driveways, sidewalks, curb, curb ramps, and a section of asphalt between Grove PL and Arcadia.  These projects will be phased and a more detailed timeline for each section will be given in the future to help keep citizens informed of the work.

TxDOT does not foresee the need to cut off access to existing businesses, but some facilities may have limited access.  TxDOT will have Traffic Control Plans and individuals on-site to help direct traffic.

The first project will begin tomorrow, Tuesday September 26, 2017 around the Historic Trolley stop at Broadway and Patterson.

  • The right hand turn lane to Patterson will be shut down, as well as the southbound lane adjacent to the stop.